TUTF Reporting and Submission Guidelines

 

 



This page provides information in relation to TUTF submission and reporting requirements for TUTF project leads. Updated project plans and budgets are required annually to inform annual allocations alongside formal progress reporting which is required on a bi-annual basis.

The following information provides you with updated guidelines that are a key part of the terms and conditions as laid out in the Technological University Transformation Fund (TUTF) HEA Advice Note.

 

Reporting requirements

Interim and Annual Reports have three components

  1. A narrative report
  2. A progress report by work package
  3. A statement of expenditure

Relevant reporting templates are provided directly to TUTF project leads.

 

In Year 3 of the Fund, the Annual Report will be replaced by a final TUTF Report, capturing progress and expenditure over the lifetime of the Fund (1 September 2020-31 August 2023).

 

Monitoring and Reporting Guidelines are reviewed and updated on an ongoing basis to reflect learning and process improvements. The most recent version of the Monitoring and Reporting Guidelines is accessible in the sidebar.

 

TUTF Submission and Reporting Schedule

Quarters Quarterly progress meetings Submission and reporting requirements
Q1 01 September – 30 November December / January  n/a
Q2 0101 December 2021 – 28 February March Interim report due by 31 March

Updated project plans and budgets due by 31 March in Years 2 and 3

Q3 01 01 March – 31 May June  n/a
Q4 01 June – 31 August October Annual Report due by 30th September

Project plans and budgets aligned to annual allocations due by 1 September

Table 1: TUTF Submission and Reporting Schedule